Grid queues change the first site question.
DESNZ’s 2026 strategic-demand consultation records 96 GW of transmission demand in Great Britain’s queue at June 2025, with another 29 GW waiting at distribution level. SparkDCS’s first evidence gate therefore requires an accepted grid offer or signed private-wire route agreements, with energisation timing checked before committing the development to a service date.
DESNZ · Strategic demand consultation · SparkDCS evidence gates